Quotations are invited from reputed firms/company/dealer for installation, delivery, commissioning of Honey processing Unit at our KVK, Ranchi campus. The technical specification of the unit are as given below:

Capacity :200kg/8hrs.

Sl. No.Description of ComponentCapacity/QtyMaterial
1Pre filter tank230 KgFood grade Stainless Steel
2Gear Pump0.5 HP motor with out put capacity (2000- 2500 ) Lts/hrPipes should be of Food grade Stainless Steel
3Pre Heating Tankcut off limit- 480C and 420C  to restart heatingFood grade Stainless Steel
4Micro Fine filtersFull stainless-steel self-locking high pressure filter having poly propylene filtersmade of 40-micron size.    
5Processing TankTo achieve temperature of 600C with temperature gauge. Proper valves shall be provided for easy control of flow rate.SS 304 food grade Stainless Steel
6Moisture reduction Unittemperature of vacuum evaporation shall be 620C±20C subjected to pressure (700  to 710)mm 
7Cooling TankThrough water circulation with temperature gauge 
8Moisture Condensation UnitVolume approx. 30% of the rated capacity of the plant 
9Condensate trap2 condensate tanks of 20 ltr capacity of appropriate thickness to withstand  (700  to 710)mm HG vacuum) 
10Vacuum Pump3.0 HP, water ring vacuum Pump or diaphragm pump with similar output. Required Vacuum 700 to 710 MM Hg 
11Settling Tanks3 tanks each of volumetric capacity of 150 lts volumetric minimum so as corresponding to 230 kgs of honey 
12Control PanelIt should be  Metal clad and all function and security buttons should be neatly placed in user friendly manner 

Terms and conditions:

  1. All the components where honey comes in contact shall be of stainless steel food grade.
  2. The piping shall be of 1” dimension, made of SS 304.
  3. All the Component of Machine Pipes and Joints are made of SS 304 Food Garde Material and need a Certificate for same.
  4. This plant shall give 4 % moisture reduction at or less than 650C.
  5. This Plant will have total input time of 8 hour per shift of 200 kg of raw honey including the time of water heating in Pre heating tank. Processed tank and Moisture Reduction Tank.
  6. HMF shall NOT increase more than 10 PPM in the process.
  7. The Vacuum Pressure shall be at 710 mm Of Hg or Above During the Entire Process.
  8. Total 2 Test Trail Runs Taken After Installation and Lab test Conducted to check the Parameter whether Correct or not. Only  after that final Payment will be Made.

Quotations should reach us before 23 February 2024 failing which the quotation will not accepted.